The RM9.4 Billion Suria Strategic Energy Resources Sdn Bhd (SSER) Pipeline Scandal: Payment Of RM8.3 Billion Or 88% Of The Project Value Made Despite Only 13% Of Progressive Work Has Been Completed, The Land Has Not Been Acquired And The Laws Were Not Complied With